Risk register: exposure and priorities

Problem

Turn a list of risks into a prioritized register.

Input: lines id probability impactDays category until the end of input; probability is between 0 and 1, category is one word (AI, PEOPLE, EXTERNAL, TECH…).

Compute exposure = probability × impact. Print the risks sorted by exposure descending (on a tie, by id alphabetically), one per line:

id: P=0.40 I=20 exposure=8.00 [LEVEL] category

with LEVEL HIGH if exposure ≥ 5, MEDIUM if ≥ 2, else LOW. Then:

Total exposure: x.xx days
Suggested buffer: y days
By category: AI=.., EXTERNAL=.., ...

The buffer is the total exposure rounded up to a whole number of days. "By category" lists the sum of exposure per category with two decimals, categories in alphabetical order.

Input:

R1 0.4 20 AI
R2 0.5 10 PEOPLE
R3 0.2 25 EXTERNAL
R4 0.3 8 AI

Output:

R1: P=0.40 I=20 exposure=8.00 [HIGH] AI
R2: P=0.50 I=10 exposure=5.00 [HIGH] PEOPLE
R3: P=0.20 I=25 exposure=5.00 [HIGH] EXTERNAL
R4: P=0.30 I=8 exposure=2.40 [MEDIUM] AI
Total exposure: 20.40 days
Suggested buffer: 21 days
By category: AI=10.40, EXTERNAL=5.00, PEOPLE=5.00

Data for this lab

Your program reads its data from standard input. Download the file, then give it to your program as shown below. Start with data set 1: its expected output is given.

s5-4-data-1.txt

R1 0.4 20 AI
R2 0.5 10 PEOPLE
R3 0.2 25 EXTERNAL
R4 0.3 8 AI
What your program must print for s5-4-data-1.txt
R1: P=0.40 I=20 exposure=8.00 [HIGH] AI
R2: P=0.50 I=10 exposure=5.00 [HIGH] PEOPLE
R3: P=0.20 I=25 exposure=5.00 [HIGH] EXTERNAL
R4: P=0.30 I=8 exposure=2.40 [MEDIUM] AI
Total exposure: 20.40 days
Suggested buffer: 21 days
By category: AI=10.40, EXTERNAL=5.00, PEOPLE=5.00

Run your program first, then open this and compare line by line: your output must contain these lines exactly.

How to give the file to my program

Terminal (macOS, Linux, or Windows Command Prompt), after compiling:

java Main < s5-4-data-1.txt

Windows PowerShell does not understand <:

Get-Content s5-4-data-1.txt | java Main