Plan the first release with velocity and risks

Problem

After Sprint 3, the StudyBuddy team has these data:

  • Velocities: Sprint 1 = 14, Sprint 2 = 21, Sprint 3 = 19 points. Sprints are 2 weeks. The semester has 5 Sprints left.
  • Remaining backlog for the "spring release": Musts = 48 points, Shoulds = 30 points, Coulds = 22 points.
  • Open risks: Buddy quality not yet proven (P 0.4, impact 1 Sprint); IT hosting approval pending (P 0.2, impact 1.5 Sprints); Mei has exams in Sprint 5 (P 0.8, impact 0.3 Sprint of capacity).

Produce a release plan for the Product Owner:

  1. A forecast of how many points the team can deliver in 5 Sprints, as a range (use the lowest, average and highest velocity).
  2. Adjust the forecast for the risks (expected loss).
  3. A commitment: which priority groups you commit to, which are "likely", and which are "unlikely" — with reasons.
  4. Two actions that would increase confidence, and one early warning sign you will watch every Sprint.
  5. A short paragraph explaining the forecast to the dean, who "needs everything by the end of the semester".

Work it out on paper, in a document or here, then compare with the model answer. Your answer stays in your browser — it is never sent to or stored on the server.